If the regulated abatement work area clearance air sampling results are unacceptable, the following requirements apply:
Table 2
ASBESTOS PROJECT AIR SAMPLING REQUIREMENTS
Air Sampling Requirements by Asbestos Project & Regulated Abatement Work Area Size | Phase I B Background Air Sampling | Phase II A Work Area Preparation Air Sampling | Phase II B Asbestos Handling Air Sampling | Phase II C Final Cleaning & Clearance Air Sampling |
LARGE ASBESTOS PROJECT OR LARGE SIZE REGULATED ABATEMENT WORK AREA | Required | Required5 | Required | Required6 |
Minimum Samples | 5 Inside Regulated | 1 per decontamination extrance/exit | 5 Inside Regulated | |
Required1 | Abatement Work | 1 per negative air exhaust | Abatement Work | |
Area & 5 Outside | or per bank of 5 exhausts | Area7 & 5 Outside | ||
Regulated | 2 at critical barriers | Regulated | ||
Abatement Work | 1 outside the | Abatement Work | ||
Area in Building/Structure2 | building/structure | Area in Building/Structure2 | ||
SMALL ASBESTOS PROJECT OR SMALL SIZE REGULATED ABATEMENT WORK AREA | Required | Not Required | Required6 | |
Minimum Samples Required1 | 3 Inside Regulated Abatement Work Area & 3 Outside Regulated Abatement Work Area in Building/Structure2 | 0 | 3 Inside Regulated Abatement Work Area & 3 Outside Regulated Abatement Work Area in Building/Structure2 | |
MINOR ASBESTOS PROJECT OR MINOR SIZE REGULATED ABATEMENT WORK AREA | Not Required | Not Required | Required3,4 | |
Minimum Samples Required1 | 0 | 0 | 1 Inside Regulated Abatement Work Area & 1 Outside Regulated Abatement Work Area |
Notes:
1 For sample location and total number required, see Subparts 56-6 through 56-9 of this Part.
2 1 sample outside the building/structure if entire building/structure is regulated abatement work area.
3 Required on glove bag failure or loss of integrity, or tent failure or loss of integrity.
4 Required for an Incidental Disturbance Project or if minor size regulated abatement work area is part of small or large asbestos project.
5 Required for all OSHA Class I and Class II Friable ACM asbestos projects.
6 During IIC final cleaning stage, air sampling as per Phase IIB is required.
7 One additional inside sample shall be required for every 5,000 sq. ft. above 25,000 sq. ft. of floor space within the regulated abatement work area.
N.Y. Comp. Codes R. & Regs. Tit. 12 §§ 56-4.12