N.M. Admin. Code § 6.27.2.11

Current through Register Vol. 35, No. 21, November 5, 2024
Section 6.27.2.11 - OVERSIGHT AND IMPLEMENTATION OF PROJECTS FUNDED WHOLLY OR IN PART BY THE COUNCIL
A. The authority shall:
(1) oversee the procurement process;
(2) require the use of standardized construction documents and the use of a standardized process for change orders;
(3) review plans and specifications for compliance with the statewide adequacy standards and all applicable codes and regulations;
(4) coordinate all required reviews and approvals;
(5) require standardized reporting and use of the construction information management system (CIMS) to monitor progress of projects;
(6) conduct periodic on-site inspections and inspection of documents to ensure compliance with project specifications;
(7) ensure timely payments for completed work;
(8) on or before the 12th month following substantial completion of the project or phase, the authority will schedule a review of all project expenditures that apply to both the scope of work and to the statewide adequacy standards to insure that the overall expenditures align with the match percentages after necessary offsets and waivers as identified in the memorandum of understanding for the project; following mutual agreement on the overall and final financial project status, project balances will be reallocated by the council; all council awards must be fully reconciled and reallocated no later than eighteen (18) months after substantial completion; and
(9) maintain records for completed projects, including warranties.
B. Management and oversight involvement by the authority shall be either direct or indirect, depending on the degree of qualified personnel in the district and ability to provide proper oversight of the project. Even with respect to responsibilities granted to the district, the authority must be consulted and must approve the actions taken in order for the authority to authorize payment for the work.
C. The authority shall develop an agreement for each project defining the respective roles and responsibilities of the authority and the district. The process shall be defined in the district agreement and may include responsibilities for the following, which shall be accomplished through the use of standardized documents, procedures, and reports, the construction information management system (CIMS), and also include review, approval and payment for completed work at each phase.
(1) Pre-design phase:
(a) assist districts in developing initial scope of project and budget;
(b) assist districts in development of educational specifications where required; and
(c) assist districts in developing the request for proposals for design professionals where necessary.
(2) Design phase:
(a) prepare or assist in developing contracts for design professionals, consultants and other required services;
(b) final review and approval of the various submittal phases including but not limited to; program statement, schematic design, design development and construction documents for completeness;
(c) periodic review and validation of scope of work, budget, schedule, value engineering, and plans and specifications;
(d) issue or review invitation to bid;
(e) assist or conduct pre-bid conference;
(f) coordinate bid opening; and
(g) review and evaluate bids.
(3) Construction phase:
(a) prepare or assist in development of contracts for construction;
(b) assist or conduct pre-construction conference;
(c) coordinate weekly project meeting with architect, engineer, consultants, district personnel, contractors and sub-contractors;
(d) provide interface for understanding of issues, disputes, and mediation;
(e) review, approve and oversee changes to the work; and
(f) periodic review and validation of work to insure conformance with contract and industry standards of quality.
(4) Project close-out:
(a) verify all work complete;
(b) coordinate operations and maintenance training;
(c) review as-built drawings;
(d) approve final close-out documents;
(e) review warranties;
(f) ensure final acceptance by district;
(g) update facility information management system (FIMS) for new facilities and equipment;
(h) ensure all required documents related to the projects are properly held and archived;
(i) ensure that one-year warranty inspections are conducted and oversee any required repairs or remedies; and
(j) schedule and conduct project budget closeout review with the district.
D. The authority shall report to the council concerning the progress of projects.
(1) The authority shall identify and make recommendations to the council concerning any substantial noncompliance with any reporting requirement or condition.
(2) The authority shall identify and make recommendations to the council regarding any misfeasance or malfeasance in the implementation of the project warranting the withholding of all or part of the grant assistance for the project.

N.M. Admin. Code § 6.27.2.11

6.27.2.11 NMAC - N, 06/15/04; A, 07/15/10