Section 3.3.35.14 - REQUIREMENTS FOR ENERGY CONSERVING PRODUCTS
A. Energy-conserving products shall be energy star rated for the location installed and meet the insulation requirements in 3.3.35.14 NMAC to be eligible for the 2021 sustainable building tax credit. Energy conserving products and insulation improvements eligible for the 2021 sustainable building tax credit shall meet the applicable requirements of the most current New Mexico commercial building code, the New Mexico residential building code, the New Mexico electrical code, the New Mexico mechanical code and the New Mexico plumbing code and shall be installed under a construction permit and shall be inspected by the code official having jurisdiction.
B. Insulation products and installation eligible for consideration for a tax credit are
(1) batts and blankets made of mineral fiber and mineral wool such as fiberglass, rock, slag, wool, cotton or cellulose materials; they are available with facings that serve as vapor retarders and without facings; some products have flanges to aid in installation to framed assemblies;
(2) loose-fill insulation that uses a blown installation process for cellulose, fiberglass, mineral wool and natural wools; the R-value of the blown wall insulation material installed in closed cavities is determined by the installed thickness and density; the installed density shall meet manufactured specifications; open horizontal applications, such as for attic and floors, the R-value is verified by thickness and rated coverage; in open vertical applications the R-value shall be thickness and rated coverage as per manufacture specifications;
(3) spray polyurethane foam having an open cellular structure having a nominal density of 0.4 to 1.5 pounds per cubic foot shall have a minimum R-value of 3.6 per inch for compliance; a spray applied polyurethane foam having a closed cellular structure having a nominal density of 1.5 to less than 2.5 pounds per cubic foot shall have a minimum R-value of 5.8 per inch for compliance; the weatherproof seal placed on top of spray polyurethane foam shall protect from degradation caused by ultraviolet light, water and other normal weathering hazards; surfaces to receive the roof covering system must comply with applicable building codes and manufacturers installation recommendations;
(4) rigid insulation sheathing made from fiberglass, mineral wool, expanded polystyrene, extruded polystyrene, polyisocyanurate or polyurethane; this type of insulation may be used for roof decks, exterior walls, ceilings, basement walls, perimeter insulation or to cover window and door headers; fastening shall follow manufacturer requirements;
(5) wet insulation systems are roofing systems where insulation is installed above the waterproof membrane of a roof; installation shall meet New Mexico building code water sealing requirements;
(6) structural form wall systems made of closed cell spray foam placed in the cavity bonded to wood framing and continuous rigid board insulation on the exterior of the frame;
(7) structural insulated panels that are non-framed advanced construction system that consists of ridged foam insulation sandwiched between two sheets of board; the insulation can be expanded polystyrene foam, extruded polystyrene foam, polyurethane or polyisocyanurate foam; and
(8) insulated concrete forms (ICF) that are a system of formwork for concrete that stays in place as permanent building insulation and can be used for cast-in-place reinforced above-and below-grade concrete walls, floors and roofs; they are interlocking modular units that can be dry stacked (without mortar) and filled with concrete as a single concrete masonry unit; ICFs lock together externally and have internal metal or plastic ties to hold the outer layers of insulation to create a concrete form.
C. Eligible insulation installations shall to the extent possible, without structural framing modification, be installed in the building cavity to the R-factor listed in the prescriptive method of the latest New Mexico energy conservation code adopted by the construction industries division of the regulation and licensing department for the applicable building cavity and construction site climate zone. In no instance shall an increase in insulating R-factor less than 10 be considered for the 2021 sustainable building tax credit. Reframing involving basic structural framing of a building is not required.
D. Mandatory requirements for insulation products.
(1) R-value identification marks shall be applied by the manufacturer to each piece of insulation 12 inches or wider. Alternatively, the insulation installer shall provide a certification listing the type, manufacturer and R-value of the insulation install in each element of the building thermal envelope.
(2) For blown in or sprayed fiberglass and cellulose insulation, the initial installed thickness, settled thickness, settled R value, installed density, coverage area and number of bags installed shall be listed on the certification.
(3) For sprayed polyurethane foam insulation, the installed thickness shall be listed on the certification. The thickness of sprayed insulation shall be marked in inches and markers showing the thickness shall be installed every 300 square feet and attached to trusses or joists in attics. The numbers in the markers shall be at least one inch high and visible from the attic access opening.
(4) Fire rating of products shall follow the New Mexico commercial building code and New Mexico residential code.
(5) Foam plastic insulation shall be tested to demonstrate a flame-spread index of not more than 75 and a smoke-developed index of not more than 450.
(6) Exposed facing on insulation materials shall be fire resistant and tested and certified not to exceed a flame spread index of 25 and a smoke development index of 450. These indexes shall be shown on the insulation or packaging material or supplied by the manufacturer.
(7) Exposed foundation insulation shall have a protective rigid, opaque and weather-resistant protective covering to prevent the degradation of the insulation.
(8) Slab insulation must be suitable for applications in direct contact with soil and have a water absorption rate less than 0.3 percent when tested and a vapor permeance not greater than 2.0 perm/inch when tested.
(9) All insulation shall be properly sealed to prevent air leakage.
(10) To qualify for the 2021 sustainable building tax credit, insulation products installed shall meet the most current New Mexico energy code insulation requirements adopted by the construction industries division of the regulation and licensing department.
E. Retrofits with the following construction material or methods are not eligible for the 2021 sustainable building tax credit:
(1) logs, strawbales, adobe and rammed earth;
(2) spray-in-place polyurethane foam for interior walls or ceilings;
(3) urea formaldehyde foam insulation; and
(4) passive solar technologies using direct gain, trombe walls or mass energy storage.
F. The following are mandatory requirements for fenestration products.
(1) Fenestration products shall meet energy star requirements.
(2) The temporary label on windows shall not be removed until after inspection by the code official.
(3) All fenestration products shall be properly sealed to prevent air leakage.
G. Windows and skylights.
(1) Windows are considered part of an exterior wall when the slope is 60 degrees or more as measured from the horizontal. Where the slope of the fenestration is less than 60 degrees, the glazing is considered a skylight. Skylights are not eligible for the 2021 sustainable building tax credit.
(2) Site built fenestration or field-fabricated fenestration are not eligible for the 2021 sustainable building tax credit.
H. To qualify for an electric vehicle ready 2021 sustainable building tax credit, a commercial building shall have at least ten percent of parking spaces and for residential buildings at least one parking space with one 40 ampere, 208 volt or 240 volt dedicated branch circuit for charging electric vehicles. The termination point can be a receptacle or junction box and shall be near where electric vehicles can easily be charged. The extension cord shall be long enough to reach a vehicle and meet code and electric vehicle manufacturing requirements.

N.M. Admin. Code § 3.3.35.14

Adopted by New Mexico Register, Volume XXVI, Issue 24, December 30, 2015, eff. 12/30/2015, Repealed by New Mexico Register, Volume XXXIII, Issue 03, February 8, 2022, eff. 2/8/2022, Adopted by New Mexico Register, Volume XXXIII, Issue 13, July 12, 2022, eff. 7/12/2022