Current through Register Vol. 35, No. 23, December 10, 2024
Section 3.3.28.20 - INSPECTION OF SOLAR ENERGY SYSTEMSA. The inspections required through the application process for certification of a taxpayer's solar energy system are: (1) inspection by the building code authority for building, electrical or mechanical code compliance, as applicable to the solar energy system type; and(2) inspection for compliance with electric utility company requirements for photovoltaic systems that are interconnected to the distribution grid of that electric utility company, if applicable.B. For purposes of inspecting the solar energy system's installation, the division or its authorized representative shall have the right to inspect a solar energy system an applicant owns and the department has certified, within three years after the department's certification, upon the division providing a minimum of five days notice to the taxpayer.N.M. Admin. Code § 3.3.28.20
3.3.28.20 NMAC - N, 7-1-06; A, 1-31-08; A, 7-16-09