Section 20.9.20.54 - ADDITIONAL CLOSURE AND COMPLETION REQUIREMENTS FOR CIVIL ENGINEERING APPLICATIONS THAT USE SCRAP TIRES FOR LAND RECLAMATION
A. For completion of a civil engineering application that uses scrap tires for land reclamation, the owner or operator shall cover the site with 30 inches of compacted native soils and 6 inches of top soil to provide a 36-inch final cover that meets original grade and implement measures where necessary to control erosion and rodent intrusion.
B. Upon completion of closure, a detailed description of the location of the land reclamation site, including a plat signed by a registered surveyor, shall be filed with the appropriate county land recording agent. The description and the plat shall be filed so that it will be found during a title search and proof of the filing shall be submitted to the department. The description shall perpetually notify any potential purchaser of the property that:
(1) scrap tires have been used to reclaim the land; and
(2) if applicable, its use is restricted as described in the post-closure care plan.
C. The owner or operator shall prepare a written closure and post-closure care plan that describes the steps necessary for closure and post-closure care of the project and any anticipated future uses of the property following closure. The written plan shall include the following:
(1) a vegetation plan, if appropriate; and
(2) a monitoring and repair plan that describes methods to be used to ensure cover integrity, including but not limited to settlement, ponding, water erosion, wind erosion, and inadequate drainage.