N.M. Admin. Code § 20.5.123.2306

Current through Register Vol. 35, No. 23, December 10, 2024
Section 20.5.123.2306 - COMPETITIVE CONTRACTOR SELECTION FOR REMEDIATION AT RESPONSIBLE PARTY-LEAD SITES
A. Payments made from the fund shall be made in accordance with 20.5.123.2309 NMAC and only for work performed by contractors that were selected using a competitive procedure based upon technical merit and cost-effectiveness, as defined in this part except as provided in Subsections C and D of this section. The solicitation and evaluation of proposals are required prior to workplan approval.
B. At a minimum, the department and the owner or operator shall obtain proposals and select contractors competitively for remediation activities under 20.5.119.1922 through 20.5.119.1928 NMAC and under 20.5.120.2019 through 20.5.120.2025 NMAC, including conceptual and final remediation plans, design, construction, installation, operation and maintenance, and monitoring.
C. Competitive contractor selection is not required for the following activities:
(1) initial abatement or emergency response under 20.5.119.1902 NMAC or 20.5.120.2002 NMAC;
(2) 72 hour and 14 day reports under 20.5.119.1903 NMAC or 20.5.120.2003 NMAC;
(3) interim removal of non-aqueous phase liquid ("NAPL"), directed or approved by the department under 20.5.119.1905 or 12.5.120.2005 NMAC;
(4) interim removal of contaminated soil, directed or approved by the department under 20.5.119.1906 NMAC or 12.5.120.2006 NMAC;
(5) investigation activities under 20.5.118.1801 NMAC and 20.5.119.1907 through 20.5.119.1913 NMAC or 20.5.120.2007 through 20.5.120.2011 NMAC;
(6) development of and monitoring and reporting under a monitored natural attenuation plan under 20.5.119.1915 through 20.5.119.1921 NMAC or 20.5.120.2012 through 20.5.120.2018 NMAC;
(7) work at sites for which the owner or operator is not seeking payment, including but not limited to federal facilities and sites determined to be out of compliance pursuant to 20.5.123.2304 NMAC; or
(8) work at sites under contract as described in subsection D of this section.
D. Work at sites with releases from USTs where the owner or operator and a contractor entered into a contract approved by the department and initiated remediation prior to October 1, 1995, shall be exempt from competitive contractor selection requirements. Work at sites with releases from ASTs at which the owner or operator and a contractor entered into a contract for and initiated remediation prior to June 14, 2002, shall be exempt from competitive contractor selection requirements. The owner or operator shall obtain a contractor for any subsequent site through the competitive contractor selection process in accordance with the requirements of 20.5.123.2306 through 20.5.123.2307 NMAC.

N.M. Admin. Code § 20.5.123.2306

Adopted by New Mexico Register, Volume XXIX, Issue 16, August 28, 2018, eff. 7/31/2018, Adopted by New Mexico Register, Volume XXIX, Issue 24, December 27, 2018, eff. 12/27/2018