N.M. Admin. Code § 20.11.3.114

Current through Register Vol. 35, No. 23, December 10, 2024
Section 20.11.3.114 - CRITERIA AND PROCEDURES: CURRENTLY CONFORMING TRANSPORTATION PLAN AND TIP

There shall be a currently conforming transportation plan and currently conforming TIP at the time of project approval, or a project must meet the requirements in Subsection F of 20.11.3.104 NMAC during the 12-month lapse grace period.

A. Only one conforming transportation plan or TIP may exist in an area at any time; conformity determinations of a previous transportation plan or TIP expire once the current plan or TIP is found to conform by DOT. The conformity determination on a transportation plan or TIP shall also lapse if conformity is not determined according to the frequency requirements specified in 20.11.3.104 NMAC.
B. This criterion is not required to be satisfied at the time of project approval for a TCM specifically included in the applicable implementation plan, provided that all other relevant criteria of 20.11.3 NMAC are satisfied.

N.M. Admin. Code § 20.11.3.114

20.11.3.114 NMAC - Rn & A, 20.11.3.211 NMAC, 11/15/10