Section 19.2.2.33 - MODIFICATION OF MINE DEVELOPMENT PLAN

If the lessee determines that it is no longer feasible or economically prudent to follow the approved mine development plan, the lessee shall submit a proposed modification of the plan to the commissioner, together with the reasons that modification is required. The lessee shall seek the commissioner's approval for the modification by following the procedure set out in 19.2.2.32 NMAC. The lessee shall continue to comply with the existing mine development plan until the commissioner approves the modification. The commissioner may refuse to approve any modification that the commissioner determines is not in the best interest of the trust.