N.M. Admin. Code § 19.1.10.16

Current through Register Vol. 35, No. 23, December 10, 2024
Section 19.1.10.16 - FINAL APPROVAL OF APPLICATIONS
A.Indian nation, tribe, or pueblo: If applicable based on statute, prior to the division's final approval of an application, an applicant that is an Indian nation, tribe, or pueblo must provide the division with a copy of a resolution enacted by the Indian nation, tribe, or pueblo that provides approval for a specific CEED program grant and must include in the resolution the terms and conditions of the grant approved by the division. If such a resolution is not supplied to the division, final approval of the application shall not be issued.
B.County or municipality: If applicable based on statute, prior to the division's final approval of an application, an applicant that is a county or municipality must provide a copy of the ordinance enacted by the county or municipality that provides the county's or municipality's formal approval for a specific CEED program grant and must include in the ordinance the terms and conditions of the grant approved by the division. If such a resolution is not supplied to the division, final approval of the application shall not be issued.
C.New Mexico Mortgage Finance Authority:
(1)Required grant of authority. If applicable based on statute, prior to the division's final approval of an application from the MFA for a CEED program grant, the MFA shall provide the division with formal approval of the MFA to accept a specific CEED program grant. If this is not supplied to the division, final approval of the application shall not be issued.
(2)Project coordination. The division and the MFA shall coordinate the work done pursuant to CEED Program grants in the state to implement energy efficiency measures.
D.Contracts: For selected project applications, the division will approve and enter into contracts with grantees to implement selected community energy efficiency projects. All contracts shall have project performance measures, penalties, or other provisions that ensure the successful completion of the projects and shall require reporting on project performance, energy savings, and non-energy benefits resulting from the energy efficiency measures.

N.M. Admin. Code § 19.1.10.16

Adopted by New Mexico Register, Volume XXXIV, Issue 09, May 16, 2023, eff. 5/16/2023