Current through Register Vol. 35, No. 23, December 10, 2024
Section 17.9.568.25 - GENERAL PROVISIONS APPLICABLE TO INTERCONNECTION CUSTOMERSA. An interconnection customer is responsible for the prudent maintenance and upkeep of its interconnection equipment.B. Upon the petition of a utility, for good cause shown, the commission may require a customer with a generating facility with a rated capacity of 250 kW or less to obtain general liability insurance prior to connecting with a public utility. A utility may require that an applicant proposing to connect a generating facility with a rated capacity greater than 250 kW provide proof of insurance with reasonable limits not to exceed $1,000,000.00 or other reasonable evidence of financial responsibility.N.M. Admin. Code § 17.9.568.25
Adopted by New Mexico Register, Volume XXXIV, Issue 03, February 14, 2023, eff. 2/14/2023