N.M. Admin. Code § 17.9.568.21

Current through Register Vol. 35, No. 23, December 10, 2024
Section 17.9.568.21 - PERMISSION TO OPERATE
A. The interconnection customer may not commence operations until its interconnection application is deemed complete and the utility has issued a permission to operate (PTO). The interconnection customer shall provide the utility with at least 10 business days' notice of the anticipated start date of the generating facility.
B. Within 10 business days of receiving the notice of the anticipated start date of the generating facility, the utility may conduct an inspection of the generating facility at a time mutually agreeable to the parties. The inspection may include verification that the facility complies with applicable codes and standards, the terms of the interconnection agreement, and may include a witness test. The utility may also schedule appropriate metering replacement or programming if necessary. If the generating facility passes the inspection, the utility shall provide written notice of the passage within three business days. If a Generating Facility initially fails a utility inspection, the utility shall offer to redo the inspection at the applicant's expense at a time mutually agreeable to the parties. If the utility determines that the generating facility fails the inspection, the utility must provide the applicant with a written explanation detailing the reasons for the failure and any standards violated. If the utility determines no inspection is necessary, it shall notify the applicant within three business days of receiving the notice of the anticipated start date.
C. For simplified process and fast track generating facilities, utility approval for interconnection (i.e. permission to operate) shall normally be processed not later than 10 business days following the utility's receipt of:
(1) a completed net energy metering interconnection application, if appropriate, including all supporting documents and required payments;
(2) a completed signed interconnection agreement, if appropriate; and
(3) evidence of the applicant's final electric inspection clearance from the governmental authority having jurisdiction over the generating facility. If the 10-day period cannot be met, the utility shall notify the applicant.
D. A generating facility that has not been approved for parallel operation within one year of execution of the interconnection agreement is subject to withdrawal by utility; however, the utility may not deem the interconnection application withdrawn if:
(1) applicant provides reasonable evidence that the interconnection application is still active; or
(2) the delay is at no fault of applicant.

N.M. Admin. Code § 17.9.568.21

Adopted by New Mexico Register, Volume XXXIV, Issue 03, February 14, 2023, eff. 2/14/2023