Current through Register Vol. 35, No. 21, November 5, 2024
Section 17.7.4.10 - CONTENTS OF THE GAS UTILITY IRPThe contents of the IRP submitted by a utility providing natural gas retail service in New Mexico shall contain the utility's jurisdictional:
A. current load forecast;B. description of existing portfolio of resources;C. summary of foreseeable resource needs for the planning period;D. anticipated resources to be added during the planning period and the evaluation of various options that could reasonably be added to the utility's resource portfolio;E. a summary description of natural gas supply sources and delivery systems;F. a summary identification of critical facilities susceptible to supply-source or other failures;G. description of the public advisory process; andH. other information that may aid the commission in reviewing the utility's planning processes.N.M. Admin. Code § 17.7.4.10
17.7.4.10 NMAC - N, 4-16-07; A, 12-31-12