Current through Register Vol. 35, No. 23, December 10, 2024
Section 17.7.3.13 - COST RECOVERYA. Acceptance of the utility's statement of need and action plan does not constitute a finding of prudence or pre-approval of costs associated with acquiring additional resources.B. Any costs incurred to implement an accepted action plan shall be considered in a general rate case, resource acquisition proceeding, or appropriate application for a CCN.N.M. Admin. Code § 17.7.3.13
17.7.3.13 NMAC - N, 4-16-07, Adopted by New Mexico Register, Volume XXXIII, Issue 20, October 25, 2022, eff. 10/27/2022