N.M. Admin. Code § 17.7.3.11

Current through Register Vol. 35, No. 20, October 22, 2024
Section 17.7.3.11 - ACTION PLAN
A. The utility's action plan shall:
(1) detail the specific actions the utility shall take to implement the IRP spanning a three year period following the filing of the utility's IRP;
(2) detail the specific actions the utility shall take to develop any resource solicitations or contracting activities to fulfill the statement of need as accepted by the commission; and
(3) include a status report of the specific actions contained in the previous action plan.
B. The utility shall update the commission by filing two reports describing the utility's implementation of the action plan. These reports shall be filed in the existing IRP docket one year after the filing of the IRP, and two years after the filing of the IRP, respectively.
C. An action plan does not replace or supplant any requirements for applications for approval of resource additions set forth in New Mexico law or commission regulations.
D. The utility shall promptly notify the commission and participants of material events that would have the effect of changing the results of the utility's action plan had those events been recognized when the action plan was developed.
E. In accepting the action plan, the commission shall take into consideration contractual obligations as between the utility and any regional transmission organizations or balancing authorities of which the utility is a member.

N.M. Admin. Code § 17.7.3.11

17.7.3.11 NMAC - N, 4-16-07, Amended by New Mexico Register, Volume XXVIII, Issue 16, August 29, 2017, eff. 8/29/2017, Adopted by New Mexico Register, Volume XXXIII, Issue 20, October 25, 2022, eff. 10/27/2022