N.J. Admin. Code § 7:8-5.6

Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:8-5.6 - Stormwater runoff quantity standards
(a) This section contains the minimum design and performance standards to control stormwater runoff quantity impacts of major development.
(b) In order to control stormwater runoff quantity impacts, the design engineer shall, using the assumptions and factors for stormwater runoff calculations at N.J.A.C. 7:8-5.7, complete one of the following:
1. Demonstrate through hydrologic and hydraulic analysis that for stormwater leaving the site, postconstruction runoff hydrographs for the current and projected two-, 10-, and 100-year storm events, as defined and determined pursuant to N.J.A.C. 7:8-5.7(c) and (d), respectively, do not exceed, at any point in time, the pre-construction runoff hydrographs for the same storm events;
2. Demonstrate through hydrologic and hydraulic analysis that there is no increase, as compared to the pre-construction condition, in the peak runoff rates of stormwater leaving the site for the current and projected two-, 10-, and 100-year storm events, as defined and determined pursuant to N.J.A.C. 7:8-5.7(c) and (d), respectively, and that the increased volume or change in timing of stormwater runoff will not increase flood damage at or downstream of the site. This analysis shall include the analysis of impacts of existing land uses and projected land uses assuming full development under existing zoning and land use ordinances in the drainage area;
3. Design stormwater management measures so that the post-construction peak runoff rates for the current and projected two-, 10-, and 100-year storm events, as defined and determined pursuant to N.J.A.C. 7:8-5.7(c) and (d), respectively, are 50, 75, and 80 percent, respectively, of the preconstruction peak runoff rates. The percentages apply only to the post-construction stormwater runoff that is attributable to the portion of the site on which the proposed development or project is to be constructed; or
4. In tidal flood hazard areas, stormwater runoff quantity analysis, in accordance with (b)1, 2, and 3 above, is required unless the design engineer demonstrates through hydrologic and hydraulic analysis that the increased volume, change in timing, or increased rate of the stormwater runoff, or any combination of the three will not result in additional flood damage below the point of discharge of the major development. No analysis is required if the stormwater is discharged directly into any ocean, bay, inlet, or the reach of any watercourse between its confluence with an ocean, bay, or inlet and downstream of the first water control structure.
(c) The stormwater runoff quantity standards shall be applied at the site's boundary to each abutting lot, roadway, watercourse, or receiving storm sewer system.

N.J. Admin. Code § 7:8-5.6

Amended by 55 N.J.R. 1385(b), effective 7/17/2023