N.J. Admin. Code § 7:7A-7.10B

Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:7A-7.10B - General permit 10B- Minor road crossings
(a) General permit 10B authorizes the following activities in freshwater wetlands, transition areas, and/or State open waters:
1. Construction of one or more new road crossings necessary to gain access to an otherwise inaccessible, developable, upland site, including attendant features such as shoulders, sidewalks and embankments;
2. Expansion, widening, or upgrading of one or more existing paved or unpaved roads, including attendant features such as shoulders, sidewalks and embankments; and
3. Activities necessary to reduce horizontal curves in an existing paved road to comply with New Jersey Department of Transportation safety regulations.
(b) The Department shall issue a general permit 10B authorization only if all applicable requirements at N.J.A.C. 7:7A-5.7 and 20.3 are met and:
1. The applicant demonstrates in accordance with (d) below that there is no alternative onsite location and/or configuration for the road crossing that would provide access to the developable upland with less adverse environmental impact; and
2. The total area of freshwater wetlands, transition areas, and/or State open waters disturbed under general permit 10B shall not exceed one-quarter of an acre.
(c) Activities under general permit 10B shall minimize environmental impact as follows:
1. The applicant shall design the crossing to ensure that fish passage is unimpeded during times when the water level is at its lowest, unless the applicant demonstrates that the water body is unsuitable for habitation by fish and will remain so for the foreseeable future. The applicant shall ensure fish passage by maintaining the existing gradient and bottom contours of the water body to the extent possible, and by using arches, culverts, or other structures that will ensure fish passage;
2. The applicant shall install cross drains or other devices to ensure that the crossing does not alter the hydrology of the freshwater wetlands and/or State open waters on either side of the crossing;
3. The amount of rip-rap or other energy dissipating material used shall be the minimum necessary to prevent erosion, and shall not exceed 200 cubic yards of fill below the top of bank or high water mark, unless a larger amount is required in order to comply with the Standards for Soil Erosion and Sediment Control in New Jersey at N.J.A.C. 2:90; and
4. The cartway, shoulder, and side slopes of the roadway shall be the minimum necessary for the crossing and shall not exceed the limits in the New Jersey Department of Community Affairs' Residential Site Improvement Standards at N.J.A.C. 5:21. If the project is not a residential development, the cartway, shoulder, and side slopes of the roadway shall be the minimum necessary for safety.
(d) In evaluating whether there is an alternative onsite location and/or configuration for a road crossing under (b)1 above, the Department shall make the presumptions at (d)1 through 5 below. However, these presumptions may be rebutted based on site-specific or unusual circumstances:
1. Disturbance of a non-transition area upland would have less adverse environmental impact than disturbance of a transition area, State open water or freshwater wetland;
2. Disturbance of a transition area would have less adverse environmental impact than disturbance of a freshwater wetland or State open water;
3. Disturbance of a freshwater wetland would have less adverse environmental impact than disturbance of a State open water;
4. Expansion or upgrading of an existing and currently serviceable drive or crossing would have less adverse environmental impact than placement of a new crossing; and
5. Placement of a new crossing in an area that is already significantly disturbed would have less adverse environmental impact than disturbance of a previously undisturbed wetland and/or State open water.
(e) Mitigation shall be performed for all permanent loss and/or disturbance of 0.1 acres or greater of freshwater wetlands or State open waters. Mitigation shall be performed for permanent loss and/or disturbance of less than 0.1 acres of freshwater wetlands or State open waters unless the applicant demonstrates to the Department that all activities have been designed to avoid and minimize impacts to wetlands. For purposes of this subsection, "minimize" means that the project is configured so that most or all of it is contained in the uplands on the site, and that the wetlands are avoided to the greatest extent possible. An applicant is not required to reduce the scope of the project or to consider offsite alternatives to comply with this requirement.
1. The mitigation shall meet the substantive and procedural requirements at N.J.A.C. 7:7A-11 and shall be submitted to the Department for review and approval no later than 90-calendar days prior to the initiation of regulated activities authorized by this general permit.

N.J. Admin. Code § 7:7A-7.10B

Amended and recodified from 7:7A-5.10B by 49 N.J.R. 3849(a), effective 12/18/2017