Current through Register Vol. 56, No. 24, December 18, 2024
Section 7:7-5.1 - General permit-by-certification 10 - reconstruction of a legally existing functioning bulkhead in-place or upland of a legally existing functioning bulkhead(a) This permit-by-certification authorizes the reconstruction of a legally existing bulkhead in-place or upland of a legally existing functioning bulkhead, provided: 1. The replacement bulkhead is located upland of any wetlands;2. The construction of a bulkhead subject to wave run-up forces (that is, in a V zone as described at N.J.A.C. 7:7-9.18) shall be designed and certified by a New Jersey licensed professional engineer to withstand the forces of wave run-up;3. The structure shall not create net adverse shoreline movement downdrift, including erosion or shoaling;4. The construction shall have no adverse impact to any special areas as described at N.J.A.C. 7:7-9; and5. Clean fill from an upland source shall be used for backfill.N.J. Admin. Code § 7:7-5.1
Adopted by 47 N.J.R. 1392(a), effective 7/6/2015