N.J. Admin. Code § 7:7-23.5

Current through Register Vol. 56, No. 24, December 18, 2024
Section 7:7-23.5 - Compliance statement requirement for an application for authorization under a general permit
(a) In addition to the requirements at N.J.A.C. 7:7-23.2 and 23.4, an application for authorization under a general permit shall include a compliance statement. The compliance statement is a narrative, which shall:
1. Demonstrate that the proposed development satisfies the requirements of the applicable general permit;
2. Demonstrate, for an application for authorization under a CAFRA general permit, that the findings set forth in CAFRA at N.J.S.A. 13:19-10, and at N.J.A.C. 7:7-1.4, which must be addressed in order for the Department to issue the approval, can be made for the proposed development; and
3. Describe the characteristics of the site and the location of all proposed regulated activities, potential impacts from the construction process, and, as applicable, the operation of the development after completion and any monitoring or reporting methods that will be used.

N.J. Admin. Code § 7:7-23.5

Adopted by 47 N.J.R. 1392(a), effective 7/6/2015
Amended by 53 N.J.R. 514(b), effective 4/5/2021