Current through Register Vol. 56, No. 24, December 18, 2024
Section 7:7-17.3 - Timing of mitigation(a) Mitigation shall be performed within the applicable time period below: 1. Except for restoration of a temporary disturbance under (a)2 below, mitigation required under a general permit authorization or individual permit shall be performed prior to or concurrently with the regulated activity that causes the disturbance;2. Mitigation for any temporary disturbance shall commence immediately upon completion of the regulated activity that caused the disturbance and shall continue until completion, which shall not exceed six months after the cessation of the regulated activities that caused the disturbance; and3. Mitigation required as part of an enforcement action shall be performed in accordance with the schedule set forth in the enforcement document.(b) All mitigation shall be continued until completion according to the schedule in the approved mitigation proposal.N.J. Admin. Code § 7:7-17.3
Adopted by 47 N.J.R. 1392(a), effective 7/6/2015