Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:45-9.2 - Submission requirements(a) For each project that is subject to review by the Commission for stream corridor impact in accordance with 7:45-9.1, the applicant shall submit to the Commission a map of the project site delineating the stream corridor at a scale of one inch equals 100 feet and containing the following: 1. The 100-year flood line, verified by the Department's Division of Land Use Regulation;2. The 100-foot wide buffer along the 100-year flood line;3. The location of all improvements and/or disturbances proposed to be located within the stream corridor;4. A description of existing vegetation in the stream corridor; and5. A metes and bounds description of the project site boundary and the stream corridor boundary, both on hard copy as well as a digital rendition, either as a CAD.dxf file or ArcView shapefile. N.J. Admin. Code § 7:45-9.2