Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:31-7.3 - Risk management program and RMP-initial evaluation(a) All RMPs submitted in accordance with this subchapter shall be reviewed by the Department to determine if they comply with the requirements of 40 CFR 68.150-185 with changes specified at 7:31-7.1(c)1 and 2 and 7.2.(b) The RMPs and risk management programs of owners or operators that have an existing approved risk management program at their stationary source shall be audited or inspected in accordance with N.J.A.C. 7:31-8 for the covered processes that are already part of the approved risk management program and also for the newly regulated covered processes.(c) The RMPs of owners or operators that do not have an approved risk management program at their facility shall be reviewed by the Department to determine whether the facility has an established risk management program. Owners or operators that have at least one process hazard analysis (for Program 3 covered processes) shall be determined to have an established risk management program and shall be notified and audited or inspected in accordance with N.J.A.C. 7:31-8.(d) Approval of the risk management program for owners or operators who are audited pursuant to (c) above shall be the signing of the consent agreement or implementation of corrective actions required by the administrative order issued pursuant to 7:31-8.1(c)9.(e) Owners or operators that do not have an approved risk management program at their facility and that the Department determines do not have an established risk management program shall be notified that they are subject to workplan in accordance with N.J.A.C. 7:31-9.N.J. Admin. Code § 7:31-7.3
Amended by R.2009 d.85, effective 3/16/2009.
See: 40 N.J.R. 5109(a), 41 N.J.R. 1206(b).
Rewrote (b) and (c); and in (e), substituted "facility" for "stationary source".