Current through Register Vol. 56, No. 24, December 18, 2024
Section 7:26A-3.5 - General approval(a) Within 30 days of receipt of an application for recycling center general approval submitted pursuant to N.J.A.C. 7:26A-3.2(a), the Department will determine whether the application is administratively complete. An application is administratively complete where it satisfies the information submission requirements of N.J.A.C. 7:26A-3.2 and where a fee has been submitted pursuant to N.J.A.C. 7:26A-2. The procedures for Department review and approval of an application for a recycling center general approval are as set forth in (a)1 through 4 below and in (b) and (c) below: 1. If an application is deemed administratively complete in accordance with (a) above, the Department will, within 30 days of receipt of the application, issue a letter to applicant indicating the administrative completeness of the application.2. If an application fails to meet the criteria for administrative completeness in accordance with (a) above, the Department will advise the applicant that the application is incomplete and will specify in writing what additional data, reports, specifications, plans or other information is required for administrative completeness, and a deadline by which such additional information shall be submitted. The Department shall not make a decision on any application until such time as the applicant has submitted the requested additional information. Failure to submit the requested additional information as required shall constitute cause for denial of the application without prejudice. A determination of incompleteness shall stop any review and shall stay the time limitations set forth in (a)1 above and (c) below.3. Within 30 days of receiving the notice of incompleteness, the applicant shall submit the requested additional information to the Department as an addendum to the application for a recycling center general approval ("Addendum").4. Upon receipt of the Addendum, the Department shall review the Addendum to determine administrative completeness in accordance with this subsection.(b) Within 90 days of issuance of the letter of administrative completeness, the Department will issue a general approval to operate a recycling center for a period not to exceed five years where the Department determines the following:1. That the application meets the criteria for a general approval of N.J.A.C. 7:26A-3; and2. That the applicant fails to meet any of the criteria for denial or revocation of a general approval set forth at N.J.A.C. 7:26A-3.12 and 3.13.(c) Within 90 days of the issuance of the letter of administrative completeness, the Department will issue a letter of denial of the application to operate a recycling center where the Department determines the following:1. That the application fails to meet the criteria for a general approval of N.J.A.C. 7:26A-3; or2. That the applicant meets any of the criteria for denial or revocation of a general approval set forth at N.J.A.C. 7:26A-3.12 and 3.13.(d) No recycling center shall receive Class B, Class C or Class D recyclable materials and commence operation until it has received written approval from the Department, unless operating pursuant to an exemption as set forth at N.J.A.C. 7:26A-1.4.(e) The general approval will accomplish the following:1. Authorize the receipt, storage, processing or transferring of Class B, Class C or Class D recyclable materials at the recycling center;2. Indicate the conditions of operation which shall be met by the recycling center owner or operator prior to the receipt, storage, processing or transfer of the source-separated recyclable materials approved to be received, stored, processed or transferred at the recycling center; and3. Indicate the limitations on recycling center operation, including, but not limited to: i. Limitation on the amount of contaminants which may be present in any truckload of source-separated recyclable materials received at the recycling center;ii. Limitation on the amount of residue which may be produced as a result of receiving, storing, processing or transferring source-separated recyclable materials at the recycling center; andiii. Limitation on the commingling of Class B, Class C or Class D materials at the recycling center.(f) All recycling centers receiving a general approval to operate a recycling center shall prominently post and maintain a legible sign, at or near the entrance to the recycling center, indicating that it is an approved New Jersey Department of Environmental Protection recycling center. In addition, the sign shall also indicate those items detailed in N.J.A.C. 7:26A-3.2(a)16 i and ii.N.J. Admin. Code § 7:26A-3.5
Amended by R.1996 d.577, effective 12/16/1996.
See: 28 N.J.R. 2240(a), 28 N.J.R. 5360(a).
In (a), inserted additional N.J.A.C. references and added last sentence; in (a)1, inserted 30 day time limitation; in (a)2, inserted specific information to include in report and added last three sentences; inserted (a)3 and (a)4; and in (e), inserted references to Classes C and D.
Administrative change.
See: 30 N.J.R. 3948(a).
Amended by R.2001 d.86, effective 3/5/2001.
See: 32 N.J.R. 2536(a), 33 N.J.R. 880(a).
In (a), amended N.J.A.C. reference.
Amended by R.2002 d.182, effective 6/17/2002 (operative December 17, 2002).
See: 33 N.J.R. 4273(a), 34 N.J.R. 2088(a).
In (b)2, amended the N.J.A.C. reference.
Notice of readoption with technical change.
See: 48 N.J.R. 76(a).