N.J. Admin. Code § 7:1L-2.1

Current through Register Vol. 57, No. 1, January 6, 2025
Section 7:1L-2.1 - Payment of permit application fees in installments
(a) If the fee for a permit application is more than $ 1,000, the applicant seeking the permit may pay the fee in accordance with the schedule set forth in (a)1, 2 and 3 below:
1. One-third of the total fee at the time the applicant files the application for the permit.
2. One-third of the total fee within 20 calendar days after the date specified in the notice under N.J.A.C. 7:1L-2.2, stating that the application for the permit is a "completed application"; and
3. One-third of the total fee within 20 calendar days after the date specified in the notice under N.J.A.C. 7:1L-2.2, stating that the Department has taken final action on the permit application. The due date of this final installment may be postponed in accordance with N.J.A.C. 7:1L-2.3.

N.J. Admin. Code § 7:1L-2.1