Section 7:1K-4.1 - Sequence of pollution prevention planning
(a) The Department recommends that industrial facilities conduct pollution prevention planning steps in the following order:
1. Identify all production processes, and sources as applicable, in accordance with N.J.A.C. 7:1K-4.3(b)3;
2. Group sources or production processes in accordance with N.J.A.C. 7:1K-4.2;
3. Complete Part IA of a Pollution Prevention Plan in accordance with N.J.A.C. 7:1K-4.3(b) except for the identification of production processes in accordance with N.J.A.C. 7:1K-4.3(b)3;
4. Target sources or production processes in accordance with N.J.A.C. 7:1K-4.4;
5. Complete Part II of a Pollution Prevention Plan, including setting use reduction and NPO reduction goals, in accordance with N.J.A.C. 7:1K-4.5;
6. Develop a Raw Material Substitution Certification, if applicable, in accordance with N.J.A.C. 7:1K-4.6;
7. Complete and submit a Pollution Prevention Plan Summary in accordance with N.J.A.C. 7:1K-5;
8. Request an out-of-process recycling authorization, if applicable, in accordance with N.J.A.C. 7:1K-4.7; and
9. Complete Part IB of a Pollution Prevention Plan in accordance with N.J.A.C. 7:1K-4.3(c) and submit a Pollution Prevention Plan Progress Report in accordance with N.J.A.C. 7:1K-6.