When the Department determines that the borrower is in noncompliance with any condition or requirement of these rules or with any loan award document specification or requirement, it shall notify the borrower of the noncompliance. The Department may require the borrower, its engineer, and/or contractor to take and complete corrective action within 10 working days of receipt of notice. If the borrower, its engineer, and/or contractor do not take corrective action or if it is not adequate, then the Department may issue a stop work order or withhold payment. The Department may, however, withhold payment pursuant to 7:1A-2.30 or issue a stop work order pursuant to 7:1A-2.31 without issuing a notice pursuant to this section.
N.J. Admin. Code § 7:1A-2.29
See: 16 New Jersey Register 631(a), 16 New Jersey Register 1479(a).
"Notice of noncompliance" was formerly codified at N.J.A.C. 7:1A-2.30.
N.J.A.C. references changed.