Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:13-7.34 - Permit-by-rule 34 - placement of one or more utility open-frame towers(a) Permit-by-rule 34 authorizes the placement of one or more open-frame towers to provide cellular telephone service or to support a utility line, provided the conditions at N.J.A.C. 7:13-6.7 are met and: 1. No tower and associated equipment is located within a floodway;2. No disturbance is located within 25 feet of any top of bank, unless the project lies adjacent to a lawfully existing bulkhead, retaining wall, or revetment along a tidal water or impounded fluvial water;3. The footing of each tower within a fluvial flood hazard area is constructed primarily at or below grade, such that the top of the footing lies no more than 12 inches aboveground;4. All wires and cables supported by the towers are situated at least one foot above the flood hazard area design flood elevation; and5. No trees are cleared, cut, and/or removed in a riparian zone.N.J. Admin. Code § 7:13-7.34
Adopted by 48 N.J.R. 1067(a), effective 6/20/2016