Current through Register Vol. 56, No. 23, December 2, 2024
Section 17:19-3.11 - Client agency management of design/construction projects(a) The DPMC may delegate authority to client agencies to manage design and/or construction phases of a project with a stipulated construction cost estimate.(b) The selection of firms to submit technical and cost proposals shall be in accordance with the major project selection procedures, pursuant to 17:19-3.6, or routine contracts selection procedures, pursuant to 17:19-3.7.N.J. Admin. Code § 17:19-3.11
Recodified from N.J.A.C. 17:19-5.12 and amended by R.2008 d.363, effective 12/1/2008.
See: 40 N.J.R. 3959(a), 40 N.J.R. 6825(a).
In (a), inserted "The"; and in (b), updated both N.J.A.C. references. Former N.J.A.C. 17:19-3.11, Director's authority to contract, recodified to N.J.A.C. 17:19-4.11.