Current through Register Vol. 56, No. 23, December 2, 2024
Section 17:11-9.3 - Change order(a) Any State agency requiring a change to an authorized construction project prior to occupancy shall submit a change order request to DPMC describing the needed change and reason for such change. DPMC shall approve a change order request if it meets the criteria established by DPMC, which criteria include the following:1. Compliance with all applicable codes;2. Compliance with SPR approvals and the State Space Plan;3. Compliance with executed lease documents;4. Availability of funding by the agency; and5. No adverse impact on construction or occupancy schedule.(b) In the event a change order cannot be approved because it does not meet the established criteria, DPMC shall assist the agency in developing an acceptable alternative, if necessary.(c) DPMC has sole responsibility for the authorization of any change orders.N.J. Admin. Code § 17:11-9.3
Amended by R.2008 d.228, effective 8/4/2008.
See: 40 N.J.R. 598(a), 40 N.J.R. 4599(a).
Substituted "DPMC" for "DPM&C" throughout.