Type | Number | Unit | Application | Permit | Extension |
Utility | 0 to 20 | Square Feet | $525.00 | $200.00 | $200.00 |
Openings | (SF) | ||||
20 to 200 | SF | $790.00 | $265.00 | $265.00 | |
Greater than 200 | SF | $1,185.00 | $395.00 | $395.00 | |
Poles | 1 to 10 | Unit | $330.00 | $100.00 | $100.00 |
Greater than 10 | Unit | $625.00 | $200.00 | $200.00 | |
Curb, Sidewalk, or Handicapped Ramp | 0 to 200 | Linear Feet (LF) | $395.00 | $130.00 | $130.00 |
Greater than 200 | LF | $790.00 | $265.00 | $265.00 | |
Drainage | 1 to 5 | Unit | $230.00 | $65.00 | $65.00 |
Facilities | |||||
Greater than 5 | Unit | $525.00 | $200.00 | $200.00 | |
0 to 200 | SF | $230.00 | $65.00 | $65.00 | |
Greater than 200 | SF | $525.00 | $200.00 | $200.00 | |
Landscaping, Tree Trimming, Vegetation Control, or Unclassified | Unit | $395.00 | $130.00 | $130.00 | |
Landscaping | |||||
Bridge Attachments | 0 to 100 | LF | $395.00 | $130.00 | $130.00 |
Greater Than 100 | LF | $790.00 | $265.00 | $265.00 | |
Pedestrian Overpass or Underpass | 1 | Unit | $790.00 | $265.00 | $265.00 |
Grading | Unit | $330.00 | $100.00 | $100.00 | |
Guiderail | 0 to 200 | LF | $395.00 | $130.00 | $130.00 |
Greater than 200 | LF | $790.00 | $265.00 | $265.00 | |
Test Holes or Borings | 1 to 5 | Unit | $230.00 | $65.00 | $65.00 |
Greater than 5 | Unit | $460.00 | $165.00 | $165.00 | |
Monitoring Wells | 1 to 5 | Unit | $230.00 | $65.00 | $65.00 |
Greater than 5 | Unit | $460.00 | $165.00 | $165.00 | |
Crosswalks | 1 to 4 | Unit | $230.00 | $65.00 | $65.00 |
Greater than 4 | Unit | $460.00 | $165.00 | $165.00 | |
Bus | Unit | $395.00 | $130.00 | $130.00 | |
Shelters or Benches | |||||
Banners, Decorations, or Temporary Announcements or Guide Signs | 1 to 5 | Unit | $165.00 | $35.00 | $35.00 |
Greater than 5 | Unit | $230.00 | $65.00 | $65.00 | |
Parades or Gatherings | Unit | $165.00 | $35.00 | $35.00 | |
Temporary Use | $460.00 | $165.00 | $165.00 | ||
Detours off State Highways or Vice Versa | Unit | $395.00 | $130.00 | $130.00 | |
Lane or Shoulder Closings on State Highways | Unit | $230.00 | $65.00 | $65.00 | |
Automatic Traffic Counting Procedure | Unit | $65.00 | $35.00 | $35.00 | |
Wireless Communications | Annual | Unit | $790.00 | $265.00 | $265.00 |
Site Survey | |||||
Railroad Grade Crossings | Unit | $525.00 | $200.00 | $200.00 | |
Miscellaneous | Unit | $395.00 | $130.00 | $130.00 | |
VCM Site Investigation | Unit | $ 395.00 | $ 130.00 | $ 130.00 | |
VCM Plan | Unit | $ 2,000 | $ 1,000 | NA |
N.J. Admin. Code § 16:41-8.1