N.J. Admin. Code § 13:62-9A.2

Current through Register Vol. 56, No. 21, November 4, 2024
Section 13:62-9A.2 - Track construction
(a) Design and construction of a tractor pull track must be approved by the Superintendent or designee pursuant to this section prior to the pulling event.
(b) The pulling surface shall be bounded on both sides by a hub rail constructed of either, a steel Armco guide rail, a concrete barrier, or timber backed, steel post and rail assembly. The hub rail shall be constructed parallel to the direction of the pull. The pulling surface shall be open on either end to facilitate flow onto and off of the competition surface. Adequate run-out area shall be provided at the top end to allow shut down and recovery in the event of a mechanical failure.
(c) A sketch of the entire facility including the pulling surface, spectator area, pit area, and parking area, as close as practicable to scale, with an accompanying written description of the facility shall be provided.

N.J. Admin. Code § 13:62-9A.2

Adopted by 46 N.J.R. 1885(a), effective 9/2/2014.