Section Tra 502.06 - Conceptual Study; Preliminary Estimate of Costs
(a) The department shall require a conceptual study to be conducted by the department or the municipality, if the department determines that the proposed project:
(1) Requires additional design or engineering analysis before a cost estimate can be made; or
(2) Includes unknown factors that would be part of the cost estimate.
(b) Based upon the design criteria specified in Tra 502.04(a), the bureau shall provide a preliminary estimate of the cost of the project to the applicant municipality, including the following information:
(1) The approximate scope and limit of work;
(2) The estimated total project cost; and
(3) The municipality's estimated share of the cost.

N.H. Admin. Code § Tra 502.06

#8924, eff 6-27-07

Amended by Volume XXXVI Number 10, Filed March 10, 2016, Proposed by #11037, Effective 2/22/2016, Expires 2/22/2026.