Section Tra 502.03 - State Highway Aid; Project Process Summary
(a) A municipality may apply to the department for aid to construct or reconstruct a class I, II, or III highway(s), as described in RSA 229:5, I-III.
(b) The process for a project shall include the following:
(1) A municipality shall make a request for project, as provided in Tra 502.05(a);
(2) The department shall examine the project site, as provided in Tra 502.05(c);
(3) If the department requires a conceptual study as provided in Tra 502.06(a), either the department or the municipality shall conduct a conceptual study;
(4) If the project is eligible for state highway aid, the bureau shall provide the municipality with a preliminary estimate of the project cost, as provided in Tra 502.06(b);
(5) The municipality shall make an application for state highway aid for a project as provided in Tra 502.07;
(6) For a municipally-managed project, the municipality shall provide an engineering study, preliminary plans, and final plans to the department for review and approval, as provided in Tra 502.09;
(7) For a department-managed project, the department shall provide the municipality with preliminary plans and final plans for review and comment from the municipality, as provided in Tra 502.10;
(8) After the contract(s) is awarded:
a. A municipally-managed project shall be administered by the municipality, as provided in Tra 502.12(b); and
b. A department-managed project shall be administered by the department, as provided in Tra 502.12(a); and
(9) State highway aid payments shall be made as provided in Tra 502.13.