N.H. Admin. Code § Site 301.04

Current through Register No. 50, December 12, 2024
Section Site 301.04 - Financial, Technical and Managerial Capability

Each application shall include a detailed description of the applicant's financial, technical, and managerial capability to construct and operate the proposed energy facility, as follows:

(a) Financial information shall include:
(1) A description of the applicant's experience financing other energy facilities;
(2) A description of the corporate structure of the applicant, including a chart showing the direct and indirect ownership of the applicant;
(3) A description of the applicant's financing plan for the proposed facility, including the amounts and sources of funds required for the construction and operation of the proposed facility;
(4) An explanation of how the applicant's financing plan compares with financing plans employed by the applicant or its affiliates, or, if no such plans have been employed by the applicant or its affiliates, then by unaffiliated project developers if and to the extent such information is publicly available, for energy facilities that are similar in size and type to the proposed facility, including any increased risks or costs associated with the applicant's financing plan; and
(5) Current and pro forma statements of assets and liabilities of the applicant;
(b) Technical information shall include:
(1) A description of the applicant's qualifications and experience in constructing and operating energy facilities, including projects similar to the proposed facility; and
(2) A description of the experience and qualifications of any contractors or consultants engaged or to be engaged by the applicant to provide technical support for the construction and operation of the proposed facility, if known at the time of application;
(c) Managerial information shall include:
(1) A description of the applicant's management structure for the construction and operation of the proposed facility, including an organizational chart for the applicant;
(2) A description of the qualifications of the applicant and its executive personnel to manage the construction and operation of the proposed facility; and
(3) To the extent the applicant plans to rely on contractors or consultants for the construction and operation of the proposed facility, a description of the experience and qualifications of the contractors and consultants, if known at the time of application.

N.H. Admin. Code § Site 301.04

#9183-B, eff 6-17-08

Amended by Volume XXXVI Number 01, Filed January 7, 2016, Proposed by #10994, Effective 12/16/2015, Expires 12/16/2025.