N.H. Admin. Code § Saf-C 3312.02

Current through Register No. 50, December 12, 2024
Section Saf-C 3312.02 - Notice of Violation
(a) The department or an agency shall issue a manufacturer a notice of violation and order to correct that sets forth, with specificity, areas of non-compliance, as defined in Saf-C 3302.19, that, if not corrected, shall result in the decertification of a modular building or building component.
(b) The notification pursuant to (a) above shall be in writing. In all cases, the notice shall be sent to the manufacturer, the agency of the modular building or building component involved and, if the notification was issued by the agency, to the department.
(c) Upon receipt of the notification, the manufacturer shall have no more than 30 days, or a mutually agreed upon time frame, to correct the area(s) of non-compliance. Upon verification by the department or the agency that the area(s) of non-compliance are corrected, the manufacturer shall receive a written statement from the department or an agency indicating acceptance of the corrective action.
(d) If a manufacturer has not corrected the area(s) of non-compliance described in the notification pursuant to (b) above after 30 days, or the mutually agreed upon time frame, the department shall schedule a hearing to determine whether the manufacturer's certification shall be revoked or suspended pursuant to the requirements of Saf-C 3312.03.

N.H. Admin. Code § Saf-C 3312.02

#5439, eff 7-24-92; ss by #6810, INTERIM, eff 7-25-98, EXPIRES: 11-22-98; ss by #6885, eff 11-18-98;ss by #8741, INTERIM, eff 11-18-06, EXPIRED: 5-17-07

New. #9752, eff 7-9-10

Amended by Volume XXXIX Number 16, Filed April 18, 2019, Proposed by #12737, Effective 3/8/2019, Expires 3/8/2029.