N.H. Admin. Code § Saf-C 3310.01

Current through Register No. 50, December 12, 2024
Section Saf-C 3310.01 - Post Certification Modification
(a) Prior to shipment from the manufacturer's facility, modular buildings and building components shall not be modified, with regard to structure or code compliance, without prior approval by the agency.
(b) After shipment and prior to any final building inspection or the issuance of a certificate of occupancy, a manufacturer who seeks to modify a modular building or building component shall resubmit building plans to the third party agency for review and approval.
(c) Upon approval by the agency of a modification to a modular building or building component pursuant to (b) above, the agency shall submit the approved modification to the department.
(d) The department or agency shall conduct an inspection of the approved modification to a modular building or building component, as necessary to insure compliance with the law and these rules.
(e) The records pursuant to (b) above shall include at a minimum, the following:
(1) A description of the modification;
(2) Statement of compliance with the applicable codes, laws, and rules;
(3) Date of approval; and
(4) Identification of the location of the modular building or building component where the modification was incorporated.
(f) The manufacturer shall maintain a record of all post-certification modifications pursuant to this section.

N.H. Admin. Code § Saf-C 3310.01

#5439, eff 7-24-92; amd by #5935, eff 12-20-94; amd by #6810, INTERIM, eff 7-25-98, EXPIRES: 11-22-98; ss by #6885, eff 11-18-98; ss by #8741, INTERIM, eff 11-18-06, EXPIRED: 5-17-07

New. #9752, eff 7-9-10 (from Saf-C 3306.05)

Amended by Volume XXXIX Number 16, Filed April 18, 2019, Proposed by #12737, Effective 3/8/2019, Expires 3/8/2029.