N.H. Admin. Code § Res 8404.06

Current through Register No. 50, December 12, 2024
Section Res 8404.06 - Summer Trail Grading Operations

Any project for summer trail grading operations shall include the following to be submitted with the application:

(a) A trail map, identifying the areas to be graded;
(b) The total one-way mileage of trails to be graded;
(c) A grading schedule that includes grading frequencies for areas identified in (a) above; and
(d) A detailed description of the grading equipment to be used including the make, model and size.

N.H. Admin. Code § Res 8404.06

#2221, eff 12-23-82; ss by #2979, eff 2-21-85; ss by #4391-a, eff 3-30-88; ss by #5698, eff 9-7-93, EXPIRED 9-7-99

New. #7238, eff 5-1-00, EXPIRED: 5-1-08

New. #9195, INTERIM, eff 6-27-08, EXPIRES: 12-24-08; ss by #9350, eff 12-24-08

Amended by Volume XXXV Number 27, Filed July 9, 2015 , Proposed by #10850, Effective 6/17/2015, Expires6/17/2025.