N.H. Admin. Code § Puc 904.06

Current through Register No. 50, December 12, 2024
Section Puc 904.06 - Upgrades or Changes in the Net Metering Facility
(a) The customer-generator shall provide to the distribution utility a written update regarding any of the information required to be provided in the interconnection application as any such changes occur.
(b) The customer-generator shall re-certify to the distribution utility the applicable certifications required by Puc 904.05(c) and (d), if any of the following occurs:
(1) The generation capacity of the facility is increased or its source is changed;
(2) Any key component of the facility, such as the inverter, is replaced or upgraded; or
(3) The relays for a non-inverter facility are replaced, rewired, or upgraded.

N.H. Admin. Code § Puc 904.06

#7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09

New. #9515, eff 7-18-09 (from Puc 904.05 ); ss by #9998, eff 9-20-11

Amended by Volume XL Number 33, Filed August 13, 2020, Proposed by #13080, Effective 9/14/2020, Expires 9/14/2030