Current through Register No. 50, December 12, 2024
Section Puc 806.05 - Marking Certain Newly Installed Underground Facilities(a) Upon completing the installation of new underground facilities within an area that has been subject to excavator notification and premarking pursuant to Puc 805.01, an operator shall make reasonable efforts to communicate the existence of such new facilities if they are covered with soil or other material that impairs their visibility.(b) For purposes of (a) above, reasonable efforts shall include: (1) Marking the tolerance zone in accordance with Puc 806.01, 806.02, 806.03, and 806.04;(2) Contacting the excavator with information regarding the presence of the newly constructed underground facilities; or(3) Leaving a tag or marker clearly indicating the presence of the newly constructed underground facilities with contact information.N.H. Admin. Code § Puc 806.05
Amended by Volume XXXVII Number 10, Filed March 9, 2017, Proposed by #12102, Effective 2/8/2017, Expires 2/8/2027.