N.H. Admin. Code § Puc 410.07

Current through Register No. 45, November 7, 2024
Section Puc 410.07 - Denial of Interconnection Requests
(a) A carrier may submit a request for interconnection at a technically feasible point not listed in Puc 410.06 (c).
(b) A carrier whose request for interconnection at a point not listed in Puc 410.06(c) is denied by an ILEC shall be permitted to petition the commission for a hearing as to whether the denial should be reversed.
(c) The commission shall reverse an ILEC's denial of a carrier's request for interconnection at a point not listed in Puc 410.06 (c) unless the ILEC proves that interconnection at that point is not technically feasible.
(d) Previous successful interconnection at the particular point using particular facilities, or at substantially similar points in networks employing substantially similar facilities, shall constitute substantial evidence of technical feasibility for interconnection at a particular point.

N.H. Admin. Code § Puc 410.07

#10542, eff 3-12-14 (See Revision Note #2 at chapter heading for Puc 400)

Ss by #10542, eff 3/12/2014 (See Revision Note #2 at chapter heading for Puc 400).