Current through Register No. 50, December 12, 2024
Section Puc 406.03 - Significant Facility Disruption(a) ELECs and ILECs shall report significant facility disruptions by e-mail notification to TelOutages@puc.nh.gov within 120 minutes of occurrence.(b) The e-mail notification sent pursuant to (a) above shall accept reply messages from the commission.(c) In the event the ELEC or ILEC does not receive confirmation of receipt of the e-mail from the commission, it shall place a call to the commission's main number to report the significant facility disruption.(d) ELECs and ILECs shall report significant facility disruptions in writing to the commission on Form T-5 Facility Disruption Report as described in Puc 409.05, which shall be filed within 10 days of the disruption.N.H. Admin. Code § Puc 406.03
#8348, eff 5-10-05 (See Revision Note #1 at chapter heading for Puc 400); ss by #10542, eff 3-12-14 (See Revision Note #2 at chapter heading for Puc 400)
Ss by #10542, eff 3/12/2014 (See Revision Note #2 at chapter heading for Puc 400).