N.H. Admin. Code § Puc 308.03

Current through Register No. 50, December 12, 2024
Section Puc 308.03 - E-3 Annual Report of Total Electric Meter Tests

Each utility shall on an annual basis complete a report of total electric meter tests on Form E-3 dated 10/2013 and available at the commission website at www.puc.nh.gov/forms, and file one signed original and one electronic copy with the commission.

N.H. Admin. Code § Puc 308.03

#2011, eff 5-4-82; ss by #2912, eff 11-26-84; ss by #4999, eff 11-26-90; ss by #6381, INTERIM, eff 11-27-97, EXPIRED: 3-27-97

New. #6605, eff 10-21-97; ss by #8448, eff 10-18-05

Adopted byVolume XXXIV Number 24, Filed June 12, 2014, Proposed by #10603, Effective 5/21/2014, Expires5/21/2024 .