N.H. Admin. Code § Puc 2502.09

Current through Register No. 50, December 12, 2024
Section Puc 2502.09 - Class III source

"Class III source" means a generation facility that began operation prior to January 1, 2006, and produces electricity from eligible electric biomass technologies having a gross nameplate capacity of 25 megawatts or less, or from methane gas, except as specified in RSA 362-F:4, III(b). Class III sources do not include, for electricity production commencing January 1, 2017, methane gas if the production is from a source or sources which began operation prior to January 1, 2006 and which source exceeds, or sources exceed, a total gross nameplate capacity of 10 megawatts in the aggregate located at any single landfill site, with all phases, stages, cells, lifts, expansions, and other landfill areas combined in determining the single landfill site gross nameplate capacity and only class III and potential class III eligible sources at any single landfill site are included in determining whether the 10 megawatt aggregate limitation has been exceeded.

N.H. Admin. Code § Puc 2502.09

#9037, INTERIM, eff 11-27-07, EXPIRED: 5-25-08

New. #9169, eff 6-3-08

Amended byVolume XXXV Number 01, Filed January 8, 2015, Proposed by #10741, Effective 12/5/2014.
Amended by Volume XXXVIII Number 06, Filed February 8, 2018, Proposed by #12473, Effective 2/1/2018, Expires 2/1/2028.