N.H. Admin. Code § Puc 1803.01

Current through Register No. 50, December 12, 2024
Section Puc 1803.01 - Design Approval Required
(a) No building design shall be considered approved pursuant to Puc 1800 and RSA 155-D without the issuance of an approval number by the commission, except as provided in (b) and (c) below.
(b) A building design that a local authority having jurisdiction has approved in writing pursuant to RSA 155-D:4, II shall be deemed approved pursuant to (a) above.
(c) Pursuant to RSA 155-D:5, II, a building design shall be deemed approved for which:
(1) Plans have been certified as complying with the energy code by an architect or engineer pursuant to RSA 155-D:4,VI; or
(2) Plans have been deemed to be approved due to failure of the commission to act on a completed application within 15 working days of submittal pursuant to RSA 155-D:4, V.

N.H. Admin. Code § Puc 1803.01

#4702, eff 11-16-89; ss by #6152, INTERIM, eff 12-26-95, EXPIRED 4-24-96

New. #6333, eff 9-17-96; ss by #6879, eff 2-1-99, EXPIRED: 2-1-07

New. #8811, INTERIM, eff 2-2-07, EXPIRED: 8-1-07

New. #8958, eff 7-31-07

Amended by Volume XXXV Number 36, Filed September 10, 2015 , Proposed by #10908, Effective 8/8/2015, Expires8/8/2025.