N.H. Admin. Code § Pas 303.02

Current through Register No. 50, December 12, 2024
Section Pas 303.02 - Application for Construction and Registration
(a) Before any passenger tramway construction, modification or relocation is started, the area operator shall apply to the board on the appropriate application as set forth in Pas 305 and Pas 309.02, for the type of lift to be constructed or modified.
(b) The operator shall not proceed with construction unless:
(1) He/she has received approval from the board; or
(2) The board has not responded within 30 days of receipt of the application.
(c) Prior to initial registration of a new, modified or relocated passenger tramway, the following shall be completed and submitted to the board:
(1) A stamped certificate from the designer with original signatures that the lift meets all requirements set forth by statute and these rules;
(2) The acceptance test and inspection;
(3) A certified copy of the results of a destruction test of the wire ropeconducted by the manufacturer or a laboratory;
(4) The evacuation plans for an aerial lift; and
(5) Certification from a qualified engineer that the lift conforms to the designer's plans.
(d) Within 60 calendar days after the acceptance test, certified as-built plans shall be completed and delivered to the owner and the tramway board.

N.H. Admin. Code § Pas 303.02

#2297, eff 2-7-83; ss by #2704, eff 5-9-84, EXPIRED 5-9-90 (formerly Saf-S 1003.02)

New. #4862, eff 7-10-90; amd by #6020, eff 4-14-95; ss by #6284, eff 7-10-96; ss by #7800, eff 12-11-02, EXPIRED: 12-11-10

New. #10072, eff 1-11-12

Amended by Volume XL Number 7, Filed February 13, 2020, Proposed by #12989, Effective 2/5/2020, Expires 2/5/2030.