N.H. Admin. Code § He-P 812.07

Current through Register No. 50, December 12, 2024
Section He-P 812.07 - ASC Construction, Modifications or Renovations
(a) For new construction and for rehabilitation of an existing building, including, but not limited to certain repairs, renovations, modifications, reconstruction, and additions, construction documents, and shop drawings, including architectural, sprinkler, and fire alarm plans shall be submitted to the department 60 days prior to the start of such work.
(b) The architectural, sprinkler, and fire alarm plans in (a) above shall accurately show the room designation(s) and exact measurements of each area to be licensed, including but not limited to window and door sizes and each room's use.
(c) Architectural, sprinkler, and fire alarm plans shall be submitted to the state fire marshal's office, as required by RSA 153:10-b, V.
(d) Any licensee or applicant who wants to use performance-based designs to meet the fire safety requirements shall provide the department with documentation of fire marshal approval for such methods.
(e) The department shall review construction documents, drawings, and plans of a newly proposed or existing facility for compliance with all applicable sections of RSA 151 and He-P 812 and shall notify the applicant or licensee whether the proposal complies with these requirements.
(f) The ASC shall comply with all applicable state laws, rules, and local ordinances when undertaking construction or rehabilitation.
(g) A licensee or applicant undertaking construction or rehabilitation of a building shall comply with the following:
(1) The state fire code, Saf-C 6000, as adopted by the commissioner of the department of safety under RSA 153, and as amended pursuant to RSA 153:5, I by the state fire marshal with the board of fire control, including but not limited to at a minimum:
a. If certified either directly or through accreditation with CMS, shall meet with Ambulatory Health Care Occupancy Chapter; or
b. If not certified either directly or through accreditation with CMS, meet the appropriate chapter of the life safety code occupancy, including but not limited to business, ambulatory health care occupancy; and
(2) The state building code as defined in RSA 155-A:1, IV, as amended by the building code review board pursuant to RSA 155-A:10, V.
(h) All ASCs, newly constructed or rehabilitated, after the 2019 effective date of He-P 812 shall comply with the Facility Guidelines Institute (FGI) "Guidelines for Design and Construction of Outpatient Facilities" (2018 edition) available as listed in Appendix A.
(i) Where rehabilitation is done with an existing facility, all such work shall comply, insofar as practicable, with applicable sections of the FGI "Guidelines for Design and Construction of Outpatient Facilities" (2018 edition), available as listed in Appendix A.
(j) Per the FGI "Guidelines for Design and Construction of Outpatient Facilities" (2018 edition) available as noted in Appendix A.
(k) The department's bureau of health facilities administration shall be the authority having jurisdiction for the requirements in (h) - (j) above and shall negotiate compliance and grant waivers in accordance with He-P 812.10 as appropriate.
(l) Penetrations, holes, or other openings in fire walls, fire partitions, smoke barriers, floors and ceilings that allow the transfer of fire, heat, or smoke shall be closed and sealed using a listed or approved sealant that provides an equivalent rating as provided by the original surface.
(m) Waivers granted by the department for construction or rehabilitation under the FGI guidelines above shall not require renewal unless the underlying reason or circumstances for the waivers change.
(n) Exceptions or variances pertaining to the state fire code referenced in (h) (1) above shall be granted only by the state fire marshal.
(o) The building, including all construction and rehabilitated spaces, shall be subject to an inspection pursuant to He-P 812.09 prior to its use.

N.H. Admin. Code § He-P 812.07

#5514, eff 11-25-92; ss by #6530, eff 6-27-97, EXPIRED: 6-27-05

New. #9727-A, eff 6-18-10

Amended by Volume XXXVIII Number 28, Filed July 12, 2018, Proposed by #12557, Effective 6/26/2018, Expires 12/24/2018.
Amended by Volume XXXIX Number 50, Filed December 12, 2019, Proposed by #12926, Effective 11/26/2019, Expires 11/26/2029.