N.H. Admin. Code § Env-Wt 606.05

Current through Register No. 50, December 12, 2024
Section Env-Wt 606.05 - Docking Construction Requirements and Conditions

All tidal docking construction shall be subject to the following standard construction requirements and conditions:

(a) Work shall be done in accordance with the standard conditions in Env-Wt 307;
(b) Installation shall be done by barge or upland to prevent the driving of construction equipment in or through tidal waters/wetlands or on the bottom of the inter-tidal zone;
(c) Access by construction equipment on the high salt marsh shall be limited to that provided by Env-Wt 307 and mats shall not be dragged into location; and
(d) Construction of docks in or near essential fish habitat shall be subject to review by NHF & G and the National Marine Fisheries Service for design recommendations or time of year restrictions.

N.H. Admin. Code § Env-Wt 606.05

#2923, eff 12-10-84, EXPIRED: 12-10-90

New.#5028, eff 12-20-90; EXPIRED: 12-20-96

New.#6429, INTERIM, eff 1-18-97, EXPIRES: 5-18-97; ss by #6498-B, eff 4-23-97, EXPIRED: 4-23-05

New.#8341, eff 4-25-05 (from Env-Wt 606.08 ) (See second Revision Note at chapter heading of Env-Wt 600)

Amended by Volume XXXIX Number 28, Filed July 11, 2019, Proposed by #12806, Effective 12/15/2019, Expires 12/15/2029.