Section Env-Wr 404.05 - Design Changes
(a) No changes shall be made to the plans and specifications approved by the department, either before or during construction, unless:
(1) The changes are approved by the design engineer; and
(2) The changes are approved by the department in writing.
(b) To request a change, the owner or the owner's designee shall submit a request for the change in writing to the department, which shall include:
(1) The specific information regarding the requested change; and
(2) The reason the change is being requested.
(c) The department shall approve the change if the overall design as revised would have been approved if it had been submitted originally.
(d) The department shall notify the owner and the owner's designee, if applicable, of the decision on the request in writing. If the request is denied, the decision shall state the reason(s) for the denial.
(e) If time is of the essence, the department shall convey verbal approval prior to issuing written approval.

N.H. Admin. Code § Env-Wr 404.05

#1716, eff 2-20-81; ss by #2207, eff 12-13-82; ss by #2900, eff 11-7-84, EXPIRED 11-7-90

New. #5080, eff 2-22-91; rpld by #6462-B, eff 2-21-97

New. #8414, eff 8-20-05; ss by #10510, eff 1-22-14