Current through Register No. 50, December 12, 2024
Section Env-Wq 704.02 - Design Period(a) Sewerage pipes and structures other than pumping facilities shall be designed to accommodate flows anticipated for the projected 50-year build-out of the project service area.(b) Sewerage pumping facilities shall be designed to accommodate flows anticipated for the projected 20-year build-out of the project service area.(c) Anticipated flows shall be calculated using population projections based on historical population data from the United States Census Bureau for no less than 20 years prior to filing the application.N.H. Admin. Code § Env-Wq 704.02
(See Revision Note at chapter heading for Env-Wq 700) #8590, eff 3-25-06
Amended byVolume XXXIV Number 46, Filed November 13, 2014, Proposed by #10693, Effective 10/15/2014, Expires10/15/2024.