N.H. Admin. Code § Env-Wq 1906.05

Current through Register No. 50, December 12, 2024
Section Env-Wq 1906.05 - Water Management Plan Document
(a) The department shall prepare a water management plan document specifying the conservation measures and operational measures that will be implemented by each affected water user and affected dam operator in the WMPA to meet the protected instream flow requirements.
(b) The plan shall include an implementation schedule for each measure identified in (a) above.
(c) For affected water users engaged in agriculture or public water supply, the plan shall:
(1) Identify any local, state, or federal financial assistance programs that could provide funding for plan implementation;
(2) Estimate the amount of financial assistance available; and
(3) Estimate the schedule for receiving assistance.
(d) For affected water users engaged in agriculture or public water supply, the implementation schedule shall:
(1) Incorporate the availability and estimated schedule of financial assistance;
(2) Allow flexibility to account for unforeseen changes in availability and timetable of financial assistance if the affected water user is engaged in a good faith effort to procure such assistance.
(e) The department shall make the draft water management plan available for public review at least 30 days before the hearing and opportunity for public comment as specified in Env-Wq 1906.06.

N.H. Admin. Code § Env-Wq 1906.05

#7901, eff 5-29-03 (See Revision Note at chapter heading for Env-Wq 1900) (formerly Env-Ws 1906.05); ss by #9936, eff 5-28-11

The amended version of this section by New Hampshire Register Volume 39, Number 02, eff.12/22/2018 is not yet available.