N.H. Admin. Code § Env-Wq 1103.04

Current through Register No. 50, December 12, 2024
Section Env-Wq 1103.04 - PBF Application: Specifications

The applicant shall provide the following information regarding the pool or spa specifications:

(a) The operating volume of the pool or spa, in gallons;
(b) Materials of construction;
(c) The shape of the pool or spa and measurements, in feet and inches, of the following pool or spa dimensions:
(1) The depth from operational water level at the shallow end;
(2) The depth from operational water level at the break in depth between the shallow and deep portions of a swimming pool;
(3) The depth from operational water level at the wall of the deep end or 12 inches out from that wall, whichever is deeper;
(4) The maximum depth from operational water level at the deep end;
(5) The depth of any underwater shelves in a pool or the seat or bench in a spa;
(6) The perimeter, length, and width of the pool or spa; and
(7) For a pool, the distance from the edge of each slide to the side walls;
(d) The surface area of the pool or spa, in square feet;
(e) The slope, in feet per feet, of:
(1) The bottom of the shallow end;
(2) The transition between the shallow and deep end; and
(3) The bottom of the deep end;
(f) Details of the deck area showing compliance with Env-Wq 1108.08(b);
(g) Information on the system's hydraulics, as follows:
(1) The designed flow rate of the circulation system in gallons per minute, which for multiple filtration systems shall represent the combined flow;
(2) A calculation of the designed turnover time, in hours, based on the operating volume of the pool or spa and the designed flow rate;
(3) Calculation of total dynamic head;
(4) The type, number, and location of water inlets;
(5) Whether skimmers will be used, and if so, the number of skimmers, with the location of skimmers shown on the plans submitted pursuant to Env-Wq 1103.06(c); and
(6) Whether there is a perimeter overflow system, also known as a gutter; and
(7) Whether a surge tank, balance tank, or collection tank is used, and if so the total capacity and operating volume of the tank in gallons;
(h) Information on submerged suction outlets, other outlets, and outlet covers, as follows:
(1) The number and location of submerged suction outlets, whether they are direct suction or indirect suction, sometimes called gravity, and the manufacturer and model of the outlets;
(2) The dimensions of each outlet, including open surface area of the cover in square inches;
(3) Maximum outlet cover rating, stated in gallons per minute, of wall outlets and of floor outlets;
(4) The calculated velocity, stated in feet per second, of water passing through each outlet cover;
(5) The diameter, in inches, and schedule of all suction outlet piping, including branch outlet piping connecting sumps, with the piping shown on the plans submitted pursuant to Env-Wq 1103.06(c); and
(6) Whether there is a dedicated vacuum line;
(i) Information on flow measurement, as follows:
(1) The flow meter manufacturer and model;
(2) The range of the flow meter; and
(3) Confirmation that vacuum and PSI gauges will be installed at the circulation pump;
(j) Information on pumps, including the number and type of pumps for filters, boosters, features, and any others, and for each:
(1) The manufacturer and model of the pump;
(2) The horsepower of the pump;
(3) The maximum pump circulation rate, in gallons per minute; and
(4) The number of suction outlets for each pump;
(k) Information on the filter system, including:
(1) The type and quantity of filter(s);
(2) The manufacturer and model of the filter;
(3) The total filter area, in square feet; and
(4) The filtration rate, in gallons per minute per square foot of filter area;
(l) Information on the disinfection system that will be used, including:
(1) The type of primary disinfection system, the type of product, and the method of delivery;
(2) The manufacturer and model of the disinfection unit and manufacturer's specifications on the disinfection unit submitted with the plans submitted pursuant to Env-Wq 1103.06(c);
(3) The capacity of the disinfection unit, in pounds per day;
(4) For a salt disinfection unit, the number of cells, with the piping configuration if more than one being shown on the plans submitted pursuant to Env-Wq 1103.06(c);
(5) Whether the unit has an automated controller, and if so the manufacturer and model of the controller; and
(6) Whether the disinfection system is interlocked with the pump as required by Env-Wq 1109.08;
(m) Whether there is any supplemental water treatment system and if so, the type of system and manufacturer and model of the system;
(n) The type(s) of entrapment avoidance methods used, with the manufacturer and model of each device and specifications for each method submitted with the plans submitted pursuant to Env-Wq 1103.06(c); and
(o) Documentation that all components meet the requirements of Env-Wq 1108.22(a)(1), submitted with the plans provided pursuant to Env-Wq 1103.06.

N.H. Admin. Code § Env-Wq 1103.04

(See Revision Note at chapter heading for Env-Wq 1100) #8468, eff 11-1-05

Readopted with Amendments byVolume XXXIV Number 19, Filed May 8, 2014, Proposed by #10577, Effective 5/1/2014, Expires5/1/2024 See Revission note.
Amended by Volume XLI Number 19, Filed May 13, 2021, Proposed by #13198, Effective 5/1/2021, Expires 5/1/2031 (see Revision Note #3 at chapter heading for Env-Wq 1100)